Update from Network Rail

Dear Stakeholder,

With the final weekend of the October engineering work complete, we wanted to provide you with a brief update on what has been achieved over the past two weeks.

Work is progressing as planned and over the past two weeks, we have achieved the following:
• Balcombe Tunnel Junction – Delivery of Switch & Crossing panels
• Haywards Heath Station – conductor rail installation completed along the Ouse Valley area and signal changes completed
• Haywards Heath to Keymer Junction – signal head changes and signalling installed
• Keymer Junction to Plumpton – signal head changes completed
• Clayton Tunnel – track renewal undertaken
• Patcham to Preston Park – signalling installation
• Streat Green (Plumpton Racecourse) – Underbridge renewed
• Three Bridges to Balcombe Tunnel Junction – signal head changes
• Lewes to Newhaven – pretesting ahead of the major work
• Cooksbridge – re-railing completed

As you are aware, work will continue into November on the following dates:
• Saturday, 03 November
• Saturday, 10 November
• Saturday & Sunday, 24 and 25 November
We will be ramping up our engagement activities as we work towards the main 9-day closure in February. If you need any assistance in your planning, please do not hesitate to make contact with us.

Kind regards,
Orlagh
Orlagh Ennis
Stakeholder Engagement Manager, Brighton Main Line Improvement Project
Network Rail
1-2 Paris Garden, London, SE1 8ND

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn

Register your interest

For BHBPA events please provide your contact details below.

For events hosted by 3rd parties, please DO NOT USE THIS FORM. Instead, close this form and use the Organiser’s link provided.

loading event...

X